BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

4mm torch-on bitumen membrane on primed concrete slab: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦7,564per m²

Tender rate about ₦10,096 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 4mm torch-on bitumen membrane on primed concrete slab is ₦7,564 per m² in Abuja: ₦6,418 materials, ₦1,146 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦10,096 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialTorch-on membrane 4mm, per m21 m²12%₦4,500₦5,040
MaterialBitumen primer, per litre0.3 litre5%₦3,500₦1,102
MaterialLPG (cooking/torching gas), per kg0.25 kg-₦1,100₦275
Labour (hours)Waterproofing applicator0.35 h-₦2,620₦917
Labour (hours)Unskilled labourer0.2 h-₦1,146₦229
Materials₦6,418
Labour₦1,146
Plant₦0
Net unit rate per m²₦7,564

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦7,564₦10,096
Lagos₦8,041₦10,732
Port Harcourt₦8,020₦10,704
Ibadan₦7,014₦9,361
Osogbo (Osun)₦7,020₦9,371
Kano₦6,828₦9,114
Kaduna₦6,927₦9,245
Enugu₦7,206₦9,618
Benin City₦7,293₦9,735
Uyo₦7,584₦10,123
Jos₦6,991₦9,331
Riverine / creek site₦9,604₦12,818

Related waterproofing rates

Frequently asked questions

How much does 4mm torch-on bitumen membrane on primed concrete slab cost per m² in Nigeria?

About ₦7,564 per m² net in Abuja as at 15 October 2026, or about ₦10,096 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦8,041 per m² and the tender rate about ₦10,732 per m².

What does the rate include?

Materials (Bitumen primer, LPG (cooking/torching gas), Torch-on membrane 4mm) with waste allowances; labour (Unskilled labourer, Waterproofing applicator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/w01-4mm-torch-on-bitumen-membrane-on-primed-concrete-slab/, prices as at 15 October 2026.