Prices as at 15 October 2026, checked weekly. Base location Abuja.

Galvanised rolling shutter (manual) installed: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦58,275per m²

Tender rate about ₦77,782 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for galvanised rolling shutter (manual) installed is ₦58,275 per m² in Abuja: ₦55,000 materials, ₦3,275 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦77,782 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGalvanised rolling shutter (manual), per m21 m²-₦55,000₦55,000
Labour (hours)Welder / fabricator0.8 h-₦2,948₦2,358
Labour (hours)Unskilled labourer0.8 h-₦1,146₦917
Materials₦55,000
Labour₦3,275
Plant₦0
Net unit rate per m²₦58,275

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦58,275₦77,782
Lagos₦61,837₦82,537
Port Harcourt₦62,511₦83,437
Ibadan₦54,870₦73,238
Osogbo (Osun)₦55,256₦73,753
Kano₦53,606₦71,551
Kaduna₦54,254₦72,416
Enugu₦56,520₦75,440
Benin City₦57,136₦76,261
Uyo₦59,434₦79,329
Jos₦54,804₦73,150
Riverine / creek site₦75,102₦100,243

Related industrial buildings rates

Frequently asked questions

How much does galvanised rolling shutter (manual) installed cost per m² in Nigeria?

About ₦58,275 per m² net in Abuja as at 15 October 2026, or about ₦77,782 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦61,837 per m² and the tender rate about ₦82,537 per m².

What does the rate include?

Materials (Galvanised rolling shutter (manual)) with waste allowances; labour (Unskilled labourer, Welder / fabricator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/y03-galvanised-rolling-shutter-manual-installed/, prices as at 15 October 2026.