BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Cold-room PU panel 100mm installed: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦115,192per m²

Tender rate about ₦153,752 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for cold-room PU panel 100mm installed is ₦115,192 per m² in Abuja: ₦113,162 materials, ₦2,030 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦153,752 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialCold-room PU panel 100mm, per m21.05 m²5%₦102,641₦113,162
Labour (hours)Roofer (sheeting)0.6 h-₦2,620₦1,572
Labour (hours)Unskilled labourer0.4 h-₦1,146₦458
Materials₦113,162
Labour₦2,030
Plant₦0
Net unit rate per m²₦115,192

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦115,192₦153,752
Lagos₦122,144₦163,032
Port Harcourt₦124,144₦165,700
Ibadan₦109,128₦145,658
Osogbo (Osun)₦110,158₦147,033
Kano₦106,763₦142,502
Kaduna₦107,956₦144,094
Enugu₦112,523₦150,190
Benin City₦113,695₦151,754
Uyo₦118,282₦157,877
Jos₦109,087₦145,604
Riverine / creek site₦149,344₦199,336

Related industrial buildings rates

Frequently asked questions

How much does cold-room PU panel 100mm installed cost per m² in Nigeria?

About ₦115,192 per m² net in Abuja as at 15 October 2026, or about ₦153,752 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦122,144 per m² and the tender rate about ₦163,032 per m².

What does the rate include?

Materials (Cold-room PU panel 100mm) with waste allowances; labour (Roofer (sheeting), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/y07-cold-room-pu-panel-100mm-installed/, prices as at 15 October 2026.