12-way TPN distribution board with 12 MCBs, installed: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦160,124per unit

Tender rate about ₦213,725 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 12-way TPN distribution board with 12 MCBs, installed is ₦160,124 per unit in Abuja: ₦139,000 materials, ₦21,124 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦213,725 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialDistribution board 12-way TPN (empty)1 unit-₦85,000₦85,000
MaterialMCB single-pole 6-63A12 unit-₦4,500₦54,000
Labour (hours)Electrician6 h-₦3,029₦18,176
Labour (hours)Electrician's mate2 h-₦1,474₦2,948
Materials₦139,000
Labour₦21,124
Plant₦0
Net unit rate per unit₦160,124

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦160,124₦213,725
Lagos₦170,154₦227,112
Port Harcourt₦170,188₦227,157
Ibadan₦148,949₦198,809
Osogbo (Osun)₦149,283₦199,255
Kano₦145,113₦193,689
Kaduna₦147,137₦196,390
Enugu₦153,119₦204,375
Benin City₦154,931₦206,794
Uyo₦161,125₦215,061
Jos₦148,527₦198,245
Riverine / creek site₦203,936₦272,203

Related electrical rates

Frequently asked questions

How much does 12-way TPN distribution board with 12 MCBs, installed cost per unit in Nigeria?

About ₦160,124 per unit net in Abuja as at 15 October 2026, or about ₦213,725 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦170,154 per unit and the tender rate about ₦227,112 per unit.

What does the rate include?

Materials (Distribution board 12-way TPN (empty), MCB single-pole 6-63A) with waste allowances; labour (Electrician, Electrician's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f23-12-way-tpn-distribution-board-with-12-mcbs-installed/, prices as at 15 October 2026.