Prices as at 15 October 2026, checked weekly. Base location Abuja.

100A 4-pole manual changeover switch, installed: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦88,591per unit

Tender rate about ₦118,247 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 100A 4-pole manual changeover switch, installed is ₦88,591 per unit in Abuja: ₦75,000 materials, ₦13,591 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦118,247 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialManual changeover switch 100A 4-pole1 unit-₦75,000₦75,000
Labour (hours)Electrician4 h-₦3,029₦12,118
Labour (hours)Electrician's mate1 h-₦1,474₦1,474
Materials₦75,000
Labour₦13,591
Plant₦0
Net unit rate per unit₦88,591

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦88,591₦118,247
Lagos₦94,179₦125,705
Port Harcourt₦93,912₦125,348
Ibadan₦82,123₦109,613
Osogbo (Osun)₦82,193₦109,707
Kano₦79,943₦106,704
Kaduna₦81,101₦108,250
Enugu₦84,373₦112,617
Benin City₦85,395₦113,980
Uyo₦88,803₦118,529
Jos₦81,851₦109,251
Riverine / creek site₦112,450₦150,093

Related electrical rates

Frequently asked questions

How much does 100A 4-pole manual changeover switch, installed cost per unit in Nigeria?

About ₦88,591 per unit net in Abuja as at 15 October 2026, or about ₦118,247 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦94,179 per unit and the tender rate about ₦125,705 per unit.

What does the rate include?

Materials (Manual changeover switch 100A 4-pole) with waste allowances; labour (Electrician, Electrician's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.