Standard-gauge track UIC60 on concrete sleepers (600mm c/c) incl. ballast, sub-ballast, fastenings and welds: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦607,890per m

Tender rate about ₦811,379 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for standard-gauge track UIC60 on concrete sleepers (600mm c/c) incl. ballast, sub-ballast, fastenings and welds is ₦607,890 per m in Abuja: ₦585,103 materials, ₦7,336 labour and ₦15,451 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦811,379 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRail UIC60 (60.21 kg/m), per m2 m2%₦106,746₦217,761
MaterialPrestressed concrete sleeper, standard gauge1.67 unit1%₦120,000₦202,404
MaterialElastic rail fastening set per sleeper (clips, pads, insulators)1.67 set2%₦52,254₦89,009
MaterialTrack ballast 25-50mm crushed granite, delivered, per tonne2 tonne5%₦22,000₦46,200
MaterialSub-ballast (graded crushed stone), per tonne1.2 tonne5%₦12,000₦15,120
MaterialAluminothermic (thermite) rail weld kit0.04 unit3%₦354,578₦14,609
Plant (days)Ballast tamping machine0.002 day-₦4,355,550₦8,711
Plant (days)Hydraulic excavator 14t0.004 day-₦545,000₦2,180
Plant (days)Rail welding & grinding unit0.001667 day-₦564,560₦941
Plant (days)Tipper truck 20t0.006667 day-₦423,040₦2,820
Plant (days)Vibratory roller 16-20t0.00125 day-₦639,020₦799
Labour (hours)Rail track worker3.5 h-₦1,965₦6,878
Labour (hours)Rail welder (thermite)0.08 h-₦5,731₦458
Materials₦585,103
Labour₦7,336
Plant₦15,451
Net unit rate per m₦607,890

Scope note: Per metre of single track. Formation excluded.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦607,890₦811,379
Lagos₦644,356₦860,052
Port Harcourt₦655,568₦875,017
Ibadan₦576,395₦769,342
Osogbo (Osun)₦582,188₦777,074
Kano₦564,326₦753,233
Kaduna₦570,397₦761,336
Enugu₦594,412₦793,389
Benin City₦600,719₦801,807
Uyo₦624,806₦833,958
Jos₦576,557₦769,558
Riverine / creek site₦790,335₦1,054,897

Related railways rates

Frequently asked questions

How much does standard-gauge track UIC60 on concrete sleepers (600mm c/c) incl. ballast, sub-ballast, fastenings and welds cost per m in Nigeria?

About ₦607,890 per m net in Abuja as at 15 October 2026, or about ₦811,379 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦644,356 per m and the tender rate about ₦860,052 per m.

What does the rate include?

Materials (Aluminothermic (thermite) rail weld kit, Elastic rail fastening set per sleeper (clips, Prestressed concrete sleeper, Rail UIC60 (60.21 kg/m), Sub-ballast (graded crushed stone), Track ballast 25-50mm crushed granite) with waste allowances; labour (Rail track worker, Rail welder (thermite)) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Ballast tamping machine, Hydraulic excavator 14t, Rail welding & grinding unit, Tipper truck 20t, Vibratory roller 16-20t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Per metre of single track. Formation excluded.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/l01-standard-gauge-track-uic60-on-concrete-sleepers-600mm-c/, prices as at 15 October 2026.