Ballast top-up and tamping: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦15,274per m

Tender rate about ₦20,387 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for ballast top-up and tamping is ₦15,274 per m in Abuja: ₦9,240 materials, ₦590 labour and ₦5,444 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦20,387 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialTrack ballast 25-50mm crushed granite, delivered, per tonne0.4 tonne5%₦22,000₦9,240
Plant (days)Ballast tamping machine0.00125 day-₦4,355,550₦5,444
Labour (hours)Rail track worker0.3 h-₦1,965₦590
Materials₦9,240
Labour₦590
Plant₦5,444
Net unit rate per m₦15,274

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦15,274₦20,387
Lagos₦16,148₦21,553
Port Harcourt₦16,419₦21,915
Ibadan₦14,422₦19,249
Osogbo (Osun)₦14,594₦19,479
Kano₦14,208₦18,963
Kaduna₦14,318₦19,110
Enugu₦14,862₦19,837
Benin City₦15,075₦20,122
Uyo₦15,626₦20,857
Jos₦14,519₦19,379
Riverine / creek site₦20,283₦27,072

Related railways rates

Frequently asked questions

How much does ballast top-up and tamping cost per m in Nigeria?

About ₦15,274 per m net in Abuja as at 15 October 2026, or about ₦20,387 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦16,148 per m and the tender rate about ₦21,553 per m.

What does the rate include?

Materials (Track ballast 25-50mm crushed granite) with waste allowances; labour (Rail track worker) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Ballast tamping machine) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/l04-ballast-top-up-and-tamping/, prices as at 15 October 2026.