BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Friction buffer stop installed: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦17,201,860per unit

Tender rate about ₦22,960,129 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for friction buffer stop installed is ₦17,201,860 per unit in Abuja: ₦16,795,800 materials, ₦31,440 labour and ₦374,620 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦22,960,129 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFriction buffer stop1 unit-₦16,795,800₦16,795,800
Plant (days)Mobile crane 25t0.5 day-₦749,240₦374,620
Labour (hours)Rail track worker16 h-₦1,965₦31,440
Materials₦16,795,800
Labour₦31,440
Plant₦374,620
Net unit rate per unit₦17,201,860

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦17,201,860₦22,960,129
Lagos₦18,230,854₦24,333,576
Port Harcourt₦18,573,922₦24,791,484
Ibadan₦16,337,051₦21,805,828
Osogbo (Osun)₦16,510,929₦22,037,911
Kano₦15,999,563₦21,355,367
Kaduna₦16,168,464₦21,580,807
Enugu₦16,852,164₦22,493,373
Benin City₦17,028,243₦22,728,394
Uyo₦17,712,257₦23,641,379
Jos₦16,343,915₦21,814,989
Riverine / creek site₦22,393,592₦29,889,777

Related railways rates

Frequently asked questions

How much does friction buffer stop installed cost per unit in Nigeria?

About ₦17,201,860 per unit net in Abuja as at 15 October 2026, or about ₦22,960,129 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦18,230,854 per unit and the tender rate about ₦24,333,576 per unit.

What does the rate include?

Materials (Friction buffer stop) with waste allowances; labour (Rail track worker) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/l05-friction-buffer-stop-installed/, prices as at 15 October 2026.