Galvanised Z-purlin 150mm fixed to trusses: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦9,547per m

Tender rate about ₦12,742 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for galvanised Z-purlin 150mm fixed to trusses is ₦9,547 per m in Abuja: ₦8,941 materials, ₦606 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦12,742 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGalvanised Z/C purlin 150x65x2, per m (4.1 kg/m)1.05 m5%₦7,728₦8,521
MaterialBolt & nut M16x100 grade 8.8 with washers0.5 unit5%₦800₦420
Labour (hours)Steel erector0.15 h-₦3,275₦491
Labour (hours)Unskilled labourer0.1 h-₦1,146₦115
Materials₦8,941
Labour₦606
Plant₦0
Net unit rate per m₦9,547

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦9,547₦12,742
Lagos₦10,131₦13,523
Port Harcourt₦10,232₦13,656
Ibadan₦8,978₦11,984
Osogbo (Osun)₦9,037₦12,063
Kano₦8,769₦11,705
Kaduna₦8,877₦11,848
Enugu₦9,247₦12,342
Benin City₦9,348₦12,477
Uyo₦9,724₦12,979
Jos₦8,966₦11,968
Riverine / creek site₦12,289₦16,403

Related steelwork rates

Frequently asked questions

How much does galvanised Z-purlin 150mm fixed to trusses cost per m in Nigeria?

About ₦9,547 per m net in Abuja as at 15 October 2026, or about ₦12,742 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦10,131 per m and the tender rate about ₦13,523 per m.

What does the rate include?

Materials (Bolt & nut M16x100 grade 8.8 with washers, Galvanised Z/C purlin 150x65x2) with waste allowances; labour (Steel erector, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/s03-galvanised-z-purlin-150mm-fixed-to-trusses/, prices as at 15 October 2026.