BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Wrought-iron burglary-proof to windows, supply & fix: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦35,229per m²

Tender rate about ₦47,022 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for wrought-iron burglary-proof to windows, supply & fix is ₦35,229 per m² in Abuja: ₦35,000 materials, ₦229 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦47,022 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWrought-iron burglary-proof - supply & fix1 m²-₦35,000₦35,000
Labour (hours)Unskilled labourer0.2 h-₦1,146₦229
Materials₦35,000
Labour₦229
Plant₦0
Net unit rate per m²₦35,229

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦35,229₦47,022
Lagos₦37,348₦49,850
Port Harcourt₦38,018₦50,744
Ibadan₦33,433₦44,625
Osogbo (Osun)₦33,772₦45,077
Kano₦32,722₦43,676
Kaduna₦33,079₦44,152
Enugu₦34,483₦46,027
Benin City₦34,838₦46,500
Uyo₦36,245₦48,378
Jos₦33,429₦44,619
Riverine / creek site₦45,752₦61,068

Related steelwork rates

Frequently asked questions

How much does wrought-iron burglary-proof to windows, supply & fix cost per m² in Nigeria?

About ₦35,229 per m² net in Abuja as at 15 October 2026, or about ₦47,022 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦37,348 per m² and the tender rate about ₦49,850 per m².

What does the rate include?

Materials (Wrought-iron burglary-proof - supply & fix) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/s05-wrought-iron-burglary-proof-to-windows-supply-and-fix/, prices as at 15 October 2026.