BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

150mm hollow sandcrete blockwork in cement-sand mortar 1:6: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦10,266per m²

Tender rate about ₦13,703 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 150mm hollow sandcrete blockwork in cement-sand mortar 1:6 is ₦10,266 per m² in Abuja: ₦8,833 materials, ₦1,433 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦13,703 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material6" (150mm) hollow sandcrete block10 unit5%₦700₦7,350
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.099 bag3%₦12,000₦1,224
MaterialSharp sand, per tonne0.033 tonne8%₦6,500₦232
MaterialWater, per m30.008 m³-₦3,500₦28.00
Labour (hours)Mason / bricklayer0.35 h-₦2,456₦860
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦8,833
Labour₦1,433
Plant₦0
Net unit rate per m²₦10,266

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦10,266₦13,703
Lagos₦10,911₦14,563
Port Harcourt₦10,901₦14,550
Ibadan₦9,538₦12,731
Osogbo (Osun)₦9,555₦12,753
Kano₦9,290₦12,399
Kaduna₦9,421₦12,575
Enugu₦9,803₦13,084
Benin City₦9,920₦13,241
Uyo₦10,316₦13,770
Jos₦9,509₦12,692
Riverine / creek site₦13,059₦17,431

Related masonry rates

Frequently asked questions

How much does 150mm hollow sandcrete blockwork in cement-sand mortar 1:6 cost per m² in Nigeria?

About ₦10,266 per m² net in Abuja as at 15 October 2026, or about ₦13,703 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦10,911 per m² and the tender rate about ₦14,563 per m².

What does the rate include?

Materials (6" (150mm) hollow sandcrete block, OPC 42.5 cement, Sharp sand, Water) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/c02-150mm-hollow-sandcrete-blockwork-in-cement-sand-mortar-1/, prices as at 15 October 2026.