BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

225mm solid block walling in mortar 1:6: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦15,024per m²

Tender rate about ₦20,053 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 225mm solid block walling in mortar 1:6 is ₦15,024 per m² in Abuja: ₦13,174 materials, ₦1,850 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦20,053 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material9" (225mm) solid block10 unit5%₦1,050₦11,025
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.146 bag3%₦12,000₦1,805
MaterialSharp sand, per tonne0.049 tonne8%₦6,500₦344
Labour (hours)Mason / bricklayer0.45 h-₦2,456₦1,105
Labour (hours)Unskilled labourer0.65 h-₦1,146₦745
Materials₦13,174
Labour₦1,850
Plant₦0
Net unit rate per m²₦15,024

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦15,024₦20,053
Lagos₦15,962₦21,306
Port Harcourt₦15,985₦21,336
Ibadan₦13,995₦18,680
Osogbo (Osun)₦14,034₦18,732
Kano₦13,639₦18,205
Kaduna₦13,826₦18,455
Enugu₦14,390₦19,208
Benin City₦14,559₦19,433
Uyo₦15,142₦20,210
Jos₦13,958₦18,631
Riverine / creek site₦19,161₦25,575

Related masonry rates

Frequently asked questions

How much does 225mm solid block walling in mortar 1:6 cost per m² in Nigeria?

About ₦15,024 per m² net in Abuja as at 15 October 2026, or about ₦20,053 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦15,962 per m² and the tender rate about ₦21,306 per m².

What does the rate include?

Materials (9" (225mm) solid block, OPC 42.5 cement, Sharp sand) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/c07-225mm-solid-block-walling-in-mortar-1-6/, prices as at 15 October 2026.