BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

125mm hollow blockwork partition in mortar 1:6: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦8,521per m²

Tender rate about ₦11,373 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 125mm hollow blockwork partition in mortar 1:6 is ₦8,521 per m² in Abuja: ₦7,268 materials, ₦1,253 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦11,373 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material5" (125mm) hollow block10 unit5%₦580₦6,090
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.08 bag3%₦12,000₦989
MaterialSharp sand, per tonne0.027 tonne8%₦6,500₦190
Labour (hours)Mason / bricklayer0.3 h-₦2,456₦737
Labour (hours)Unskilled labourer0.45 h-₦1,146₦516
Materials₦7,268
Labour₦1,253
Plant₦0
Net unit rate per m²₦8,521

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦8,521₦11,373
Lagos₦9,057₦12,089
Port Harcourt₦9,040₦12,066
Ibadan₦7,907₦10,554
Osogbo (Osun)₦7,917₦10,567
Kano₦7,699₦10,276
Kaduna₦7,809₦10,423
Enugu₦8,125₦10,845
Benin City₦8,223₦10,975
Uyo₦8,551₦11,414
Jos₦7,882₦10,521
Riverine / creek site₦10,827₦14,451

Related masonry rates

Frequently asked questions

How much does 125mm hollow blockwork partition in mortar 1:6 cost per m² in Nigeria?

About ₦8,521 per m² net in Abuja as at 15 October 2026, or about ₦11,373 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦9,057 per m² and the tender rate about ₦12,089 per m².

What does the rate include?

Materials (5" (125mm) hollow block, OPC 42.5 cement, Sharp sand) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/c05-125mm-hollow-blockwork-partition-in-mortar-1-6/, prices as at 15 October 2026.