BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Manual call point with 15m FP cable in conduit: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦112,310per unit

Tender rate about ₦149,906 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for manual call point with 15m FP cable in conduit is ₦112,310 per unit in Abuja: ₦107,398 materials, ₦4,912 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦149,906 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialAddressable manual call point1 unit-₦74,648₦74,648
MaterialFire-resistant cable 2-core 1.5mm2 (FP200-type), per m15 m5%₦1,800₦28,350
Material20mm PVC conduit, 3m4 length10%₦1,000₦4,400
Labour (hours)Fire systems technician1.2 h-₦4,094₦4,912
Materials₦107,398
Labour₦4,912
Plant₦0
Net unit rate per unit₦112,310

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦112,310₦149,906
Lagos₦119,147₦159,032
Port Harcourt₦120,657₦161,046
Ibadan₦105,958₦141,427
Osogbo (Osun)₦106,786₦142,533
Kano₦103,565₦138,232
Kaduna₦104,786₦139,863
Enugu₦109,180₦145,728
Benin City₦110,352₦147,292
Uyo₦114,796₦153,223
Jos₦105,860₦141,296
Riverine / creek site₦145,021₦193,567

Related fire, hvac, lifts & ict rates

Frequently asked questions

How much does manual call point with 15m FP cable in conduit cost per unit in Nigeria?

About ₦112,310 per unit net in Abuja as at 15 October 2026, or about ₦149,906 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦119,147 per unit and the tender rate about ₦159,032 per unit.

What does the rate include?

Materials (20mm PVC conduit, Addressable manual call point, Fire-resistant cable 2-core 1.5mm2 (FP200-type)) with waste allowances; labour (Fire systems technician) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/x03-manual-call-point-with-15m-fp-cable-in-conduit/, prices as at 15 October 2026.