BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Sprinkler head with 3m 1" galvanised branch pipe and hangers: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦33,270per unit

Tender rate about ₦44,408 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for sprinkler head with 3m 1" galvanised branch pipe and hangers is ₦33,270 per unit in Abuja: ₦27,621 materials, ₦5,649 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦44,408 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialSprinkler head pendent 68degC K5.61 unit2%₦11,197₦11,421
MaterialGalvanised pipe 1" medium, 6m (2.41 kg/m)0.5 length5%₦27,257₦14,310
MaterialExpansion anchor bolt M122 unit5%₦900₦1,890
Labour (hours)Plumber1.5 h-₦2,784₦4,176
Labour (hours)Plumber's mate1 h-₦1,474₦1,474
Materials₦27,621
Labour₦5,649
Plant₦0
Net unit rate per unit₦33,270

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦33,270₦44,408
Lagos₦35,380₦47,223
Port Harcourt₦35,198₦46,980
Ibadan₦30,760₦41,056
Osogbo (Osun)₦30,753₦41,048
Kano₦29,925₦39,942
Kaduna₦30,370₦40,537
Enugu₦31,588₦42,162
Benin City₦31,977₦42,682
Uyo₦33,252₦44,383
Jos₦30,647₦40,905
Riverine / creek site₦42,122₦56,222

Related fire, hvac, lifts & ict rates

Frequently asked questions

How much does sprinkler head with 3m 1" galvanised branch pipe and hangers cost per unit in Nigeria?

About ₦33,270 per unit net in Abuja as at 15 October 2026, or about ₦44,408 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦35,380 per unit and the tender rate about ₦47,223 per unit.

What does the rate include?

Materials (Expansion anchor bolt M12, Galvanised pipe 1" medium, Sprinkler head pendent 68degC K5.6) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/x05-sprinkler-head-with-3m-1-galvanised-branch-pipe-and-hang/, prices as at 15 October 2026.