BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Fire hose reel cabinet installed with 12m 1" supply: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦520,667per unit

Tender rate about ₦694,959 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for fire hose reel cabinet installed with 12m 1" supply is ₦520,667 per unit in Abuja: ₦507,240 materials, ₦13,428 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦694,959 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFire hose reel 30m in cabinet, complete1 unit-₦450,000₦450,000
MaterialGalvanised pipe 1" medium, 6m (2.41 kg/m)2 length5%₦27,257₦57,240
Labour (hours)Plumber4 h-₦2,784₦11,135
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Materials₦507,240
Labour₦13,428
Plant₦0
Net unit rate per unit₦520,667

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦520,667₦694,959
Lagos₦552,176₦737,015
Port Harcourt₦560,575₦748,226
Ibadan₦492,620₦657,523
Osogbo (Osun)₦497,021₦663,397
Kano₦481,804₦643,086
Kaduna₦487,279₦650,394
Enugu₦507,837₦677,834
Benin City₦513,178₦684,963
Uyo₦533,870₦712,582
Jos₦492,351₦657,164
Riverine / creek site₦674,182₦899,862

Related fire, hvac, lifts & ict rates

Frequently asked questions

How much does fire hose reel cabinet installed with 12m 1" supply cost per unit in Nigeria?

About ₦520,667 per unit net in Abuja as at 15 October 2026, or about ₦694,959 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦552,176 per unit and the tender rate about ₦737,015 per unit.

What does the rate include?

Materials (Fire hose reel 30m in cabinet, Galvanised pipe 1" medium) with waste allowances; labour (Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/x06-fire-hose-reel-cabinet-installed-with-12m-1-supply/, prices as at 15 October 2026.