BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Galvanised ductwork with insulation installed: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦35,492per m²

Tender rate about ₦47,372 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for galvanised ductwork with insulation installed is ₦35,492 per m² in Abuja: ₦31,955 materials, ₦3,537 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦47,372 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGalvanised sheet ductwork (fabricated), per m2 of duct surface1.1 m²8%₦22,000₦26,136
MaterialGlass/rock wool insulation 50mm, per m21.1 m²8%₦4,500₦5,346
MaterialExpansion anchor bolt M120.5 unit5%₦900₦472
Labour (hours)AC / HVAC technician0.8 h-₦3,275₦2,620
Labour (hours)Unskilled labourer0.8 h-₦1,146₦917
Materials₦31,955
Labour₦3,537
Plant₦0
Net unit rate per m²₦35,492

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦35,492₦47,372
Lagos₦37,692₦50,309
Port Harcourt₦37,871₦50,548
Ibadan₦33,186₦44,295
Osogbo (Osun)₦33,329₦44,486
Kano₦32,370₦43,206
Kaduna₦32,796₦43,774
Enugu₦34,145₦45,575
Benin City₦34,535₦46,096
Uyo₦35,920₦47,944
Jos₦33,116₦44,201
Riverine / creek site₦45,432₦60,640

Related fire, hvac, lifts & ict rates

Frequently asked questions

How much does galvanised ductwork with insulation installed cost per m² in Nigeria?

About ₦35,492 per m² net in Abuja as at 15 October 2026, or about ₦47,372 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦37,692 per m² and the tender rate about ₦50,309 per m².

What does the rate include?

Materials (Expansion anchor bolt M12, Galvanised sheet ductwork (fabricated), Glass/rock wool insulation 50mm) with waste allowances; labour (AC / HVAC technician, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/x11-galvanised-ductwork-with-insulation-installed/, prices as at 15 October 2026.