Prices as at 15 October 2026, checked weekly. Base location Abuja.

Topographic survey with total station (in-house): cost per ha in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦19,571per ha

Tender rate about ₦26,122 per ha with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for topographic survey with total station (in-house) is ₦19,571 per ha in Abuja: ₦0 materials, ₦12,071 labour and ₦7,500 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦26,122 per ha.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Total station0.3 day-₦25,000₦7,500
Labour (hours)Land surveyor2.4 h-₦2,410₦5,783
Labour (hours)Chainman / survey assistant4.8 h-₦1,310₦6,288
Materials₦0
Labour₦12,071
Plant₦7,500
Net unit rate per ha₦19,571

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per haTender rate incl. OH&P and VAT
Abuja (FCT)₦19,571₦26,122
Lagos₦20,912₦27,912
Port Harcourt₦19,568₦26,118
Ibadan₦16,782₦22,400
Osogbo (Osun)₦16,328₦21,794
Kano₦16,178₦21,594
Kaduna₦16,540₦22,077
Enugu₦17,007₦22,700
Benin City₦17,398₦23,222
Uyo₦17,985₦24,006
Jos₦16,690₦22,278
Riverine / creek site₦23,778₦31,738

Related site, testing & surveys rates

Frequently asked questions

How much does topographic survey with total station (in-house) cost per ha in Nigeria?

About ₦19,571 per ha net in Abuja as at 15 October 2026, or about ₦26,122 per ha as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦20,912 per ha and the tender rate about ₦27,912 per ha.

What does the rate include?

Materials (no materials) with waste allowances; labour (Chainman / survey assistant, Land surveyor) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Total station) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/z07-topographic-survey-with-total-station-in-house/, prices as at 15 October 2026.