Site hoarding 2.4m, corrugated sheets on timber posts, painted: cost per m in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦21,291per m
Tender rate about ₦28,418 per m with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for site hoarding 2.4m, corrugated sheets on timber posts, painted is ₦21,291 per m in Abuja: ₦17,361 materials, ₦3,930 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦28,418 per m.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Corrugated galvanised sheet for hoarding, per sheet | 1 sheet | 5% | ₦9,500 | ₦9,975 |
| Material | 2"x4"x12' hardwood (Gmelina/Akpontu) | 0.6 length | 10% | ₦4,800 | ₦3,168 |
| Material | 2"x3"x12' hardwood | 0.6 length | 10% | ₦3,500 | ₦2,310 |
| Material | Wire nails, assorted, per kg | 0.3 kg | 10% | ₦2,600 | ₦858 |
| Material | Emulsion paint, per litre | 0.4 litre | 5% | ₦2,500 | ₦1,050 |
| Labour (hours) | Carpenter (formwork & roof) | 1 h | - | ₦2,784 | ₦2,784 |
| Labour (hours) | Unskilled labourer | 1 h | - | ₦1,146 | ₦1,146 |
| Materials | ₦17,361 | ||||
| Labour | ₦3,930 | ||||
| Plant | ₦0 | ||||
| Net unit rate per m | ₦21,291 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦21,291 | ₦28,418 |
| Lagos | ₦22,647 | ₦30,228 |
| Port Harcourt | ₦22,483 | ₦30,010 |
| Ibadan | ₦19,637 | ₦26,210 |
| Osogbo (Osun) | ₦19,614 | ₦26,180 |
| Kano | ₦19,093 | ₦25,485 |
| Kaduna | ₦19,385 | ₦25,874 |
| Enugu | ₦20,158 | ₦26,906 |
| Benin City | ₦20,410 | ₦27,242 |
| Uyo | ₦21,222 | ₦28,326 |
| Jos | ₦19,558 | ₦26,105 |
| Riverine / creek site | ₦26,892 | ₦35,894 |
Related site, testing & surveys rates
- Z01 Concrete cube test, set of 3 incl. sampling₦15,573 per set
- Z02 Geotechnical borehole with SPT (service)₦35,000 per m
- Z03 Cone penetration test (service)₦18,000 per m
- Z04 Plate load test incl. reaction load₦722,500 per unit
- Z05 Static pile load test up to 300t incl. attendance₦10,025,990 per unit
- Z06 High-strain dynamic pile test (PDA)₦650,000 per unit
- Z07 Topographic survey with total station (in-house)₦19,571 per ha
- Z08 Setting out with surveyor and 2 chainmen₦65,237 per day
- Z10 Field density test (sand replacement)₦15,000 per unit
- Z11 CBR test₦30,000 per unit
- Z12 Rebar tensile and bend test₦25,000 per unit
- Z13 Ultrasonic weld test, per joint₦20,000 per unit
- Z14 Asphalt core and extraction test₦40,000 per unit
- Z15 Water quality analysis (full suite)₦85,000 per unit
Frequently asked questions
How much does site hoarding 2.4m, corrugated sheets on timber posts, painted cost per m in Nigeria?
About ₦21,291 per m net in Abuja as at 15 October 2026, or about ₦28,418 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦22,647 per m and the tender rate about ₦30,228 per m.
What does the rate include?
Materials (2"x3"x12' hardwood, 2"x4"x12' hardwood (Gmelina/Akpontu), Corrugated galvanised sheet for hoarding, Emulsion paint, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/z09-site-hoarding-2-4m-corrugated-sheets-on-timber-posts-pai/, prices as at 15 October 2026.