Ultrasonic weld test, per joint: cost per unit in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦20,000per unit
Tender rate about ₦26,695 per unit with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for ultrasonic weld test, per joint is ₦20,000 per unit in Abuja: ₦20,000 materials, ₦0 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦26,695 per unit.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Ultrasonic weld test, per joint | 1 unit | - | ₦20,000 | ₦20,000 |
| Materials | ₦20,000 | ||||
| Labour | ₦0 | ||||
| Plant | ₦0 | ||||
| Net unit rate per unit | ₦20,000 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per unit | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦20,000 | ₦26,695 |
| Lagos | ₦21,200 | ₦28,297 |
| Port Harcourt | ₦21,600 | ₦28,831 |
| Ibadan | ₦19,000 | ₦25,360 |
| Osogbo (Osun) | ₦19,200 | ₦25,627 |
| Kano | ₦18,600 | ₦24,826 |
| Kaduna | ₦18,800 | ₦25,093 |
| Enugu | ₦19,600 | ₦26,161 |
| Benin City | ₦19,800 | ₦26,428 |
| Uyo | ₦20,600 | ₦27,496 |
| Jos | ₦19,000 | ₦25,360 |
| Riverine / creek site | ₦26,000 | ₦34,703 |
Related site, testing & surveys rates
- Z01 Concrete cube test, set of 3 incl. sampling₦15,573 per set
- Z02 Geotechnical borehole with SPT (service)₦35,000 per m
- Z03 Cone penetration test (service)₦18,000 per m
- Z04 Plate load test incl. reaction load₦722,500 per unit
- Z05 Static pile load test up to 300t incl. attendance₦10,025,990 per unit
- Z06 High-strain dynamic pile test (PDA)₦650,000 per unit
- Z07 Topographic survey with total station (in-house)₦19,571 per ha
- Z08 Setting out with surveyor and 2 chainmen₦65,237 per day
- Z09 Site hoarding 2.4m, corrugated sheets on timber posts, painted₦21,291 per m
- Z10 Field density test (sand replacement)₦15,000 per unit
- Z11 CBR test₦30,000 per unit
- Z12 Rebar tensile and bend test₦25,000 per unit
- Z14 Asphalt core and extraction test₦40,000 per unit
- Z15 Water quality analysis (full suite)₦85,000 per unit
Frequently asked questions
How much does ultrasonic weld test, per joint cost per unit in Nigeria?
About ₦20,000 per unit net in Abuja as at 15 October 2026, or about ₦26,695 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦21,200 per unit and the tender rate about ₦28,297 per unit.
What does the rate include?
Materials (Ultrasonic weld test) with waste allowances; labour (no labour) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.