BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

15mm internal plaster, cement-sand 1:6, to blockwork: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦3,202per m²

Tender rate about ₦4,274 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 15mm internal plaster, cement-sand 1:6, to blockwork is ₦3,202 per m² in Abuja: ₦1,417 materials, ₦1,785 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦4,274 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.094 bag3%₦12,000₦1,162
MaterialPlaster sand, per tonne0.031 tonne8%₦7,000₦234
MaterialWater, per m30.006 m³-₦3,500₦21.00
Labour (hours)Plasterer / screeder0.6 h-₦2,211₦1,326
Labour (hours)Unskilled labourer0.4 h-₦1,146₦458
Materials₦1,417
Labour₦1,785
Plant₦0
Net unit rate per m²₦3,202

Scope note: Check: 9.4 bags/100 m2 (market 8-12).

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦3,202₦4,274
Lagos₦3,430₦4,578
Port Harcourt₦3,226₦4,306
Ibadan₦2,774₦3,703
Osogbo (Osun)₦2,699₦3,603
Kano₦2,657₦3,546
Kaduna₦2,724₦3,636
Enugu₦2,817₦3,760
Benin City₦2,867₦3,826
Uyo₦2,977₦3,973
Jos₦2,739₦3,655
Riverine / creek site₦3,806₦5,080

Related finishes rates

Frequently asked questions

How much does 15mm internal plaster, cement-sand 1:6, to blockwork cost per m² in Nigeria?

About ₦3,202 per m² net in Abuja as at 15 October 2026, or about ₦4,274 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,430 per m² and the tender rate about ₦4,578 per m².

What does the rate include?

Materials (OPC 42.5 cement, Plaster sand, Water) with waste allowances; labour (Plasterer / screeder, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Check: 9.4 bags/100 m2 (market 8-12).

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e01-15mm-internal-plaster-cement-sand-1-6-to-blockwork/, prices as at 15 October 2026.