As at 15 October 2026, the net unit rate for 2 coats weathershield paint to external render is ₦1,612 per m² in Abuja: ₦998 materials, ₦614 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦2,151 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWeathershield, per litre0.2 litre5%₦4,750₦998
Labour (hours)Painter0.3 h-₦2,047₦614
Materials₦998
Labour₦614
Plant₦0
Net unit rate per m²₦1,612

Scope note: Scaffolding in prelims.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦1,612₦2,151
Lagos₦1,721₦2,296
Port Harcourt₦1,661₦2,217
Ibadan₦1,439₦1,921
Osogbo (Osun)₦1,418₦1,893
Kano₦1,388₦1,853
Kaduna₦1,417₦1,891
Enugu₦1,469₦1,960
Benin City₦1,491₦1,990
Uyo₦1,549₦2,068
Jos₦1,427₦1,904
Riverine / creek site₦1,972₦2,632

Related finishes rates

Frequently asked questions

How much does 2 coats weathershield paint to external render cost per m² in Nigeria?

About ₦1,612 per m² net in Abuja as at 15 October 2026, or about ₦2,151 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦1,721 per m² and the tender rate about ₦2,296 per m².

What does the rate include?

Materials (Weathershield) with waste allowances; labour (Painter) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Scaffolding in prelims.