300x600 wall tiles on adhesive, grouted: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦13,736per m²

Tender rate about ₦18,334 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 300x600 wall tiles on adhesive, grouted is ₦13,736 per m² in Abuja: ₦11,239 materials, ₦2,497 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦18,334 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWall tile 300x6001 m²10%₦7,500₦8,250
MaterialTile adhesive, standard, 20kg0.25 bag5%₦9,500₦2,494
MaterialTile grout, per kg0.3 kg10%₦1,500₦495
Labour (hours)Tiler0.9 h-₦2,456₦2,211
Labour (hours)Unskilled labourer0.25 h-₦1,146₦287
Materials₦11,239
Labour₦2,497
Plant₦0
Net unit rate per m²₦13,736

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦13,736₦18,334
Lagos₦14,610₦19,501
Port Harcourt₦14,510₦19,367
Ibadan₦12,675₦16,917
Osogbo (Osun)₦12,662₦16,901
Kano₦12,325₦16,451
Kaduna₦12,512₦16,701
Enugu₦13,012₦17,367
Benin City₦13,174₦17,584
Uyo₦13,699₦18,284
Jos₦12,625₦16,851
Riverine / creek site₦17,357₦23,168

Related finishes rates

Frequently asked questions

How much does 300x600 wall tiles on adhesive, grouted cost per m² in Nigeria?

About ₦13,736 per m² net in Abuja as at 15 October 2026, or about ₦18,334 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦14,610 per m² and the tender rate about ₦19,501 per m².

What does the rate include?

Materials (Tile adhesive, Tile grout, Wall tile 300x600) with waste allowances; labour (Tiler, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e06-300x600-wall-tiles-on-adhesive-grouted/, prices as at 15 October 2026.