₦27,280per m²

Tender rate about ₦36,412 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for natural stone wall cladding on adhesive is ₦27,280 per m² in Abuja: ₦24,480 materials, ₦2,800 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦36,412 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialNatural stone wall cladding, per m21 m²8%₦18,000₦19,440
MaterialTile adhesive, flexible/porcelain grade (C2TE), 20kg0.3 bag5%₦16,000₦5,040
Labour (hours)Tiler1 h-₦2,456₦2,456
Labour (hours)Unskilled labourer0.3 h-₦1,146₦344
Materials₦24,480
Labour₦2,800
Plant₦0
Net unit rate per m²₦27,280

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦27,280₦36,412
Lagos₦28,973₦38,672
Port Harcourt₦29,099₦38,839
Ibadan₦25,496₦34,031
Osogbo (Osun)₦25,601₦34,171
Kano₦24,866₦33,190
Kaduna₦25,195₦33,629
Enugu₦26,230₦35,011
Benin City₦26,531₦35,413
Uyo₦27,595₦36,832
Jos₦25,440₦33,956
Riverine / creek site₦34,904₦46,588

Related finishes rates

Frequently asked questions

How much does natural stone wall cladding on adhesive cost per m² in Nigeria?

About ₦27,280 per m² net in Abuja as at 15 October 2026, or about ₦36,412 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦28,973 per m² and the tender rate about ₦38,672 per m².

What does the rate include?

Materials (Natural stone wall cladding, Tile adhesive) with waste allowances; labour (Tiler, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e24-natural-stone-wall-cladding-on-adhesive/, prices as at 15 October 2026.