BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Skim coat + 3 coats emulsion to internal plastered walls: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦2,375per m²

Tender rate about ₦3,170 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for skim coat + 3 coats emulsion to internal plastered walls is ₦2,375 per m² in Abuja: ₦1,601 materials, ₦774 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦3,170 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWall putty / skim coat, 20kg0.1 bag5%₦9,000₦945
MaterialEmulsion paint, per litre0.25 litre5%₦2,500₦656
Labour (hours)Painter0.35 h-₦2,047₦716
Labour (hours)Unskilled labourer0.05 h-₦1,146₦57.31
Materials₦1,601
Labour₦774
Plant₦0
Net unit rate per m²₦2,375

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦2,375₦3,170
Lagos₦2,533₦3,381
Port Harcourt₦2,464₦3,289
Ibadan₦2,140₦2,857
Osogbo (Osun)₦2,117₦2,826
Kano₦2,069₦2,762
Kaduna₦2,109₦2,815
Enugu₦2,188₦2,921
Benin City₦2,220₦2,963
Uyo₦2,307₦3,079
Jos₦2,125₦2,836
Riverine / creek site₦2,933₦3,914

Related finishes rates

Frequently asked questions

How much does skim coat + 3 coats emulsion to internal plastered walls cost per m² in Nigeria?

About ₦2,375 per m² net in Abuja as at 15 October 2026, or about ₦3,170 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦2,533 per m² and the tender rate about ₦3,381 per m².

What does the rate include?

Materials (Emulsion paint, Wall putty / skim coat) with waste allowances; labour (Painter, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e07-skim-coat-3-coats-emulsion-to-internal-plastered-walls/, prices as at 15 October 2026.