₦3,620per m²

Tender rate about ₦4,831 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for knot, prime & 3 coats gloss to wood or metal is ₦3,620 per m² in Abuja: ₦2,698 materials, ₦921 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦4,831 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRed oxide anti-rust primer, 4L0.03 tin5%₦22,000₦693
MaterialGloss paint (oil), 4L0.065 tin5%₦28,000₦1,911
MaterialThinner, 4L0.01 tin5%₦9,000₦94.50
Labour (hours)Painter0.45 h-₦2,047₦921
Materials₦2,698
Labour₦921
Plant₦0
Net unit rate per m²₦3,620

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦3,620₦4,831
Lagos₦3,855₦5,146
Port Harcourt₦3,789₦5,058
Ibadan₦3,300₦4,405
Osogbo (Osun)₦3,281₦4,380
Kano₦3,200₦4,272
Kaduna₦3,255₦4,345
Enugu₦3,381₦4,513
Benin City₦3,427₦4,574
Uyo₦3,562₦4,755
Jos₦3,282₦4,381
Riverine / creek site₦4,521₦6,035

Related finishes rates

Frequently asked questions

How much does knot, prime & 3 coats gloss to wood or metal cost per m² in Nigeria?

About ₦3,620 per m² net in Abuja as at 15 October 2026, or about ₦4,831 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,855 per m² and the tender rate about ₦5,146 per m².

What does the rate include?

Materials (Gloss paint (oil), Red oxide anti-rust primer, Thinner) with waste allowances; labour (Painter) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e17-knot-prime-and-3-coats-gloss-to-wood-or-metal/, prices as at 15 October 2026.