BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Sand-textured coating + 2 coats weathershield, external: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦5,073per m²

Tender rate about ₦6,771 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for sand-textured coating + 2 coats weathershield, external is ₦5,073 per m² in Abuja: ₦3,832 materials, ₦1,240 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,771 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialTextured (sand) wall coating, 25kg0.06 20L pail5%₦45,000₦2,835
MaterialWeathershield, per litre0.2 litre5%₦4,750₦998
Labour (hours)Painter0.55 h-₦2,047₦1,126
Labour (hours)Unskilled labourer0.1 h-₦1,146₦115
Materials₦3,832
Labour₦1,240
Plant₦0
Net unit rate per m²₦5,073

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦5,073₦6,771
Lagos₦5,402₦7,210
Port Harcourt₦5,317₦7,097
Ibadan₦4,633₦6,184
Osogbo (Osun)₦4,610₦6,153
Kano₦4,495₦5,999
Kaduna₦4,570₦6,100
Enugu₦4,748₦6,338
Benin City₦4,811₦6,422
Uyo₦5,002₦6,676
Jos₦4,608₦6,151
Riverine / creek site₦6,347₦8,471

Related finishes rates

Frequently asked questions

How much does sand-textured coating + 2 coats weathershield, external cost per m² in Nigeria?

About ₦5,073 per m² net in Abuja as at 15 October 2026, or about ₦6,771 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦5,402 per m² and the tender rate about ₦7,210 per m².

What does the rate include?

Materials (Textured (sand) wall coating, Weathershield) with waste allowances; labour (Painter, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e18-sand-textured-coating-2-coats-weathershield-external/, prices as at 15 October 2026.