POP screeding (skimming) to walls/ceilings: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦1,961per m²

Tender rate about ₦2,617 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for pOP screeding (skimming) to walls/ceilings is ₦1,961 per m² in Abuja: ₦1,134 materials, ₦827 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦2,617 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPlaster of Paris (POP), 40kg bag0.12 bag5%₦9,000₦1,134
Labour (hours)POP / ceiling installer0.3 h-₦2,374₦712
Labour (hours)Unskilled labourer0.1 h-₦1,146₦115
Materials₦1,134
Labour₦827
Plant₦0
Net unit rate per m²₦1,961

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦1,961₦2,617
Lagos₦2,095₦2,796
Port Harcourt₦2,010₦2,683
Ibadan₦1,739₦2,321
Osogbo (Osun)₦1,709₦2,281
Kano₦1,675₦2,235
Kaduna₦1,711₦2,284
Enugu₦1,773₦2,366
Benin City₦1,801₦2,404
Uyo₦1,871₦2,497
Jos₦1,722₦2,299
Riverine / creek site₦2,384₦3,182

Related finishes rates

Frequently asked questions

How much does pOP screeding (skimming) to walls/ceilings cost per m² in Nigeria?

About ₦1,961 per m² net in Abuja as at 15 October 2026, or about ₦2,617 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦2,095 per m² and the tender rate about ₦2,796 per m².

What does the rate include?

Materials (Plaster of Paris (POP)) with waste allowances; labour (POP / ceiling installer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e19-pop-screeding-skimming-to-walls-ceilings/, prices as at 15 October 2026.