BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Gypsum drywall partition, 12.5mm board both sides on metal studs: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦14,560per m²

Tender rate about ₦19,434 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for gypsum drywall partition, 12.5mm board both sides on metal studs is ₦14,560 per m² in Abuja: ₦12,316 materials, ₦2,243 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦19,434 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGypsum board 12.5mm, 1.2x2.4m0.72 sheet5%₦11,000₦8,316
MaterialGalvanised drywall stud/channel, 3m1.2 length5%₦2,800₦3,528
MaterialPlaster of Paris (POP), 40kg bag0.05 bag5%₦9,000₦473
Labour (hours)POP / ceiling installer0.8 h-₦2,374₦1,900
Labour (hours)Unskilled labourer0.3 h-₦1,146₦344
Materials₦12,316
Labour₦2,243
Plant₦0
Net unit rate per m²₦14,560

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦14,560₦19,434
Lagos₦15,478₦20,660
Port Harcourt₦15,433₦20,599
Ibadan₦13,495₦18,013
Osogbo (Osun)₦13,506₦18,028
Kano₦13,137₦17,534
Kaduna₦13,327₦17,789
Enugu₦13,865₦18,506
Benin City₦14,033₦18,730
Uyo₦14,593₦19,478
Jos₦13,451₦17,953
Riverine / creek site₦18,479₦24,665

Related finishes rates

Frequently asked questions

How much does gypsum drywall partition, 12.5mm board both sides on metal studs cost per m² in Nigeria?

About ₦14,560 per m² net in Abuja as at 15 October 2026, or about ₦19,434 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦15,478 per m² and the tender rate about ₦20,660 per m².

What does the rate include?

Materials (Galvanised drywall stud/channel, Gypsum board 12.5mm, Plaster of Paris (POP)) with waste allowances; labour (POP / ceiling installer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e28-gypsum-drywall-partition-12-5mm-board-both-sides-on-meta/, prices as at 15 October 2026.