Raised access floor 600x600 on adjustable pedestals: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦110,104per m²

Tender rate about ₦146,960 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for raised access floor 600x600 on adjustable pedestals is ₦110,104 per m² in Abuja: ₦108,892 materials, ₦1,212 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦146,960 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRaised access floor 600x600 with pedestals, per m21.03 m²3%₦102,641₦108,892
Labour (hours)Tiler0.4 h-₦2,456₦982
Labour (hours)Unskilled labourer0.2 h-₦1,146₦229
Materials₦108,892
Labour₦1,212
Plant₦0
Net unit rate per m²₦110,104

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦110,104₦146,960
Lagos₦116,734₦155,810
Port Harcourt₦118,754₦158,507
Ibadan₦104,417₦139,370
Osogbo (Osun)₦105,445₦140,742
Kano₦102,178₦136,382
Kaduna₦103,303₦137,884
Enugu₦107,683₦143,730
Benin City₦108,797₦145,216
Uyo₦113,189₦151,078
Jos₦104,392₦139,337
Riverine / creek site₦142,892₦190,725

Related finishes rates

Frequently asked questions

How much does raised access floor 600x600 on adjustable pedestals cost per m² in Nigeria?

About ₦110,104 per m² net in Abuja as at 15 October 2026, or about ₦146,960 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦116,734 per m² and the tender rate about ₦155,810 per m².

What does the rate include?

Materials (Raised access floor 600x600 with pedestals) with waste allowances; labour (Tiler, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/e29-raised-access-floor-600x600-on-adjustable-pedestals/, prices as at 15 October 2026.