11kV 3-core 185mm2 Cu armoured cable laid in trench: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦113,862per m

Tender rate about ₦151,977 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 11kV 3-core 185mm2 Cu armoured cable laid in trench is ₦113,862 per m in Abuja: ₦112,208 materials, ₦1,654 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦151,977 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material11kV 3-core 185mm2 Cu XLPE armoured cable, per m1.03 m3%₦105,000₦111,394
MaterialFilling sand, per tonne0.15 tonne5%₦3,500₦551
MaterialUnderground warning tape 300mm, per m1 m5%₦250₦262
Labour (hours)HV electrician0.15 h-₦4,912₦737
Labour (hours)Unskilled labourer0.8 h-₦1,146₦917
Materials₦112,208
Labour₦1,654
Plant₦0
Net unit rate per m₦113,862

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦113,862₦151,977
Lagos₦120,727₦161,140
Port Harcourt₦122,756₦163,848
Ibadan₦107,921₦144,047
Osogbo (Osun)₦108,960₦145,434
Kano₦105,594₦140,941
Kaduna₦106,766₦142,505
Enugu₦111,287₦148,540
Benin City₦112,442₦150,082
Uyo₦116,980₦156,139
Jos₦107,888₦144,003
Riverine / creek site₦147,690₦197,129

Related power distribution rates

Frequently asked questions

How much does 11kV 3-core 185mm2 Cu armoured cable laid in trench cost per m in Nigeria?

About ₦113,862 per m net in Abuja as at 15 October 2026, or about ₦151,977 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦120,727 per m and the tender rate about ₦161,140 per m.

What does the rate include?

Materials (11kV 3-core 185mm2 Cu XLPE armoured cable, Filling sand, Underground warning tape 300mm) with waste allowances; labour (HV electrician, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/n02-11kv-3-core-185mm2-cu-armoured-cable-laid-in-trench/, prices as at 15 October 2026.