BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

33kV cable termination (3 phases) installed and tested: cost per set in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦522,050per set

Tender rate about ₦696,805 per set with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 33kV cable termination (3 phases) installed and tested is ₦522,050 per set in Abuja: ₦450,000 materials, ₦72,050 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦696,805 per set.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material33kV heat-shrink termination kit (3 phases)1 set-₦450,000₦450,000
Labour (hours)HV cable jointer8 h-₦6,550₦52,400
Labour (hours)HV electrician4 h-₦4,912₦19,650
Materials₦450,000
Labour₦72,050
Plant₦0
Net unit rate per set₦522,050

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per setTender rate incl. OH&P and VAT
Abuja (FCT)₦522,050₦696,805
Lagos₦554,814₦740,536
Port Harcourt₦554,448₦740,047
Ibadan₦485,140₦647,539
Osogbo (Osun)₦486,038₦648,737
Kano₦472,538₦630,718
Kaduna₦479,199₦639,609
Enugu₦498,640₦665,558
Benin City₦504,581₦673,488
Uyo₦524,742₦700,398
Jos₦483,699₦645,616
Riverine / creek site₦664,255₦886,612

Related power distribution rates

Frequently asked questions

How much does 33kV cable termination (3 phases) installed and tested cost per set in Nigeria?

About ₦522,050 per set net in Abuja as at 15 October 2026, or about ₦696,805 per set as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦554,814 per set and the tender rate about ₦740,536 per set.

What does the rate include?

Materials (33kV heat-shrink termination kit (3 phases)) with waste allowances; labour (HV cable jointer, HV electrician) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/n03-33kv-cable-termination-3-phases-installed-and-tested/, prices as at 15 October 2026.