33kV cable straight-through joint: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦722,378per unit

Tender rate about ₦964,191 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 33kV cable straight-through joint is ₦722,378 per unit in Abuja: ₦650,000 materials, ₦72,378 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦964,191 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material33kV straight-through joint kit1 set-₦650,000₦650,000
Labour (hours)HV cable jointer10 h-₦6,550₦65,500
Labour (hours)Unskilled labourer6 h-₦1,146₦6,878
Materials₦650,000
Labour₦72,378
Plant₦0
Net unit rate per unit₦722,378

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦722,378₦964,191
Lagos₦767,168₦1,023,975
Port Harcourt₦770,759₦1,028,768
Ibadan₦675,402₦901,491
Osogbo (Osun)₦678,283₦905,336
Kano₦658,783₦879,309
Kaduna₦667,454₦890,883
Enugu₦694,902₦927,518
Benin City₦702,850₦938,126
Uyo₦731,021₦975,728
Jos₦673,954₦899,559
Riverine / creek site₦924,615₦1,234,127

Related power distribution rates

Frequently asked questions

How much does 33kV cable straight-through joint cost per unit in Nigeria?

About ₦722,378 per unit net in Abuja as at 15 October 2026, or about ₦964,191 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦767,168 per unit and the tender rate about ₦1,023,975 per unit.

What does the rate include?

Materials (33kV straight-through joint kit) with waste allowances; labour (HV cable jointer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/n04-33kv-cable-straight-through-joint/, prices as at 15 October 2026.