BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Feeder pillar 800A installed on base: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦4,558,125per unit

Tender rate about ₦6,083,943 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for feeder pillar 800A installed on base is ₦4,558,125 per unit in Abuja: ₦4,524,720 materials, ₦33,405 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,083,943 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFeeder pillar 800A, 6-way1 unit-₦4,500,000₦4,500,000
MaterialOPC 42.5 cement, 50kg bag - adopted market average2 bag3%₦12,000₦24,720
Labour (hours)Electrician8 h-₦3,029₦24,235
Labour (hours)Unskilled labourer8 h-₦1,146₦9,170
Materials₦4,524,720
Labour₦33,405
Plant₦0
Net unit rate per unit₦4,558,125

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦4,558,125₦6,083,943
Lagos₦4,832,281₦6,449,871
Port Harcourt₦4,918,432₦6,564,862
Ibadan₦4,325,208₦5,773,058
Osogbo (Osun)₦4,368,785₦5,831,222
Kano₦4,233,043₦5,650,041
Kaduna₦4,279,293₦5,711,773
Enugu₦4,460,950₦5,954,239
Benin City₦4,506,865₦6,015,524
Uyo₦4,688,856₦6,258,436
Jos₦4,324,540₦5,772,166
Riverine / creek site₦5,918,882₦7,900,209

Related power distribution rates

Frequently asked questions

How much does feeder pillar 800A installed on base cost per unit in Nigeria?

About ₦4,558,125 per unit net in Abuja as at 15 October 2026, or about ₦6,083,943 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦4,832,281 per unit and the tender rate about ₦6,449,871 per unit.

What does the rate include?

Materials (Feeder pillar 800A, OPC 42.5 cement) with waste allowances; labour (Electrician, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/n09-feeder-pillar-800a-installed-on-base/, prices as at 15 October 2026.