Prices as at 15 October 2026, checked weekly. Base location Abuja.

11kV ring main unit installed on concrete plinth with 3 terminations: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦35,003,449per unit

Tender rate about ₦46,720,744 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for 11kV ring main unit installed on concrete plinth with 3 terminations is ₦35,003,449 per unit in Abuja: ₦34,623,444 materials, ₦149,340 labour and ₦230,665 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦46,720,744 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRing main unit 11kV 3-way SF61 unit-₦33,591,600₦33,591,600
Material11kV heat-shrink termination kit (3-core)3 set-₦280,000₦840,000
MaterialOPC 42.5 cement, 50kg bag - adopted market average6 bag3%₦12,000₦74,160
MaterialSharp sand, per tonne0.7 tonne8%₦6,500₦4,914
MaterialGranite 3/4", per tonne1.3 tonne5%₦18,000₦24,570
MaterialHigh-yield rebar 12-16mm, per tonne0.08 tonne5%₦1,050,000₦88,200
Plant (days)Hiab / truck-mounted crane 10t0.5 day-₦461,330₦230,665
Labour (hours)HV electrician16 h-₦4,912₦78,600
Labour (hours)HV cable jointer8 h-₦6,550₦52,400
Labour (hours)Unskilled labourer16 h-₦1,146₦18,340
Materials₦34,623,444
Labour₦149,340
Plant₦230,665
Net unit rate per unit₦35,003,449

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦35,003,449₦46,720,744
Lagos₦37,104,336₦49,524,896
Port Harcourt₦37,784,310₦50,432,490
Ibadan₦33,230,875₦44,354,807
Osogbo (Osun)₦33,574,256₦44,813,133
Kano₦32,530,939₦43,420,570
Kaduna₦32,881,654₦43,888,685
Enugu₦34,276,499₦45,750,449
Benin City₦34,630,333₦46,222,729
Uyo₦36,026,671₦48,086,487
Jos₦33,232,502₦44,356,978
Riverine / creek site₦45,497,682₦60,727,889

Related power distribution rates

Frequently asked questions

How much does 11kV ring main unit installed on concrete plinth with 3 terminations cost per unit in Nigeria?

About ₦35,003,449 per unit net in Abuja as at 15 October 2026, or about ₦46,720,744 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦37,104,336 per unit and the tender rate about ₦49,524,896 per unit.

What does the rate include?

Materials (11kV heat-shrink termination kit (3-core), Granite 3/4", High-yield rebar 12-16mm, OPC 42.5 cement, Ring main unit 11kV 3-way SF6, Sharp sand) with waste allowances; labour (HV cable jointer, HV electrician, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hiab / truck-mounted crane 10t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.