BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Prepaid meter single-phase installed with service cable: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦112,059per unit

Tender rate about ₦149,570 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for prepaid meter single-phase installed with service cable is ₦112,059 per unit in Abuja: ₦106,000 materials, ₦6,059 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦149,570 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPrepaid energy meter, single-phase1 unit-₦85,000₦85,000
Material6mm2 single-core Cu cable, 100m coil0.1 100m coil5%₦200,000₦21,000
Labour (hours)Electrician2 h-₦3,029₦6,059
Materials₦106,000
Labour₦6,059
Plant₦0
Net unit rate per unit₦112,059

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦112,059₦149,570
Lagos₦118,903₦158,706
Port Harcourt₦120,236₦160,484
Ibadan₦105,547₦140,879
Osogbo (Osun)₦106,304₦141,889
Kano₦103,124₦137,645
Kaduna₦104,366₦139,302
Enugu₦108,727₦145,123
Benin City₦109,908₦146,700
Uyo₦114,330₦152,602
Jos₦105,426₦140,717
Riverine / creek site₦144,465₦192,824

Related power distribution rates

Frequently asked questions

How much does prepaid meter single-phase installed with service cable cost per unit in Nigeria?

About ₦112,059 per unit net in Abuja as at 15 October 2026, or about ₦149,570 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦118,903 per unit and the tender rate about ₦158,706 per unit.

What does the rate include?

Materials (6mm2 single-core Cu cable, Prepaid energy meter) with waste allowances; labour (Electrician) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/n10-prepaid-meter-single-phase-installed-with-service-cable/, prices as at 15 October 2026.