Prices as at 15 October 2026, checked weekly. Base location Abuja.

Line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦456,678per m

Tender rate about ₦609,550 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench is ₦456,678 per m in Abuja: ₦435,735 materials, ₦10,562 labour and ₦10,382 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦609,550 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialAPI 5L X52 line pipe 24" (610.0x12.7mm, 187.1 kg/m), bare, per m1 m2%₦349,099₦356,081
Material3-layer polyethylene (3LPE) factory pipe coating, per m2 of pipe surface1.916 m²2%₦26,127₦51,060
MaterialHeat-shrink field joint sleeve 24" with primer0.08333 unit3%₦205,282₦17,620
MaterialCellulosic electrode E6010 (root pass), per kg0.25 kg10%₦8,398₦2,309
MaterialLow-hydrogen electrode E7018, per kg0.8 kg10%₦6,532₦5,748
MaterialRadiographic weld test, per joint (incl. film)0.08333 unit-₦35,000₦2,917
Labour (hours)Pipeline welder (6G coded)0.8 h-₦7,369₦5,895
Labour (hours)Pipe fitter0.5 h-₦4,912₦2,456
Labour (hours)Coating applicator0.15 h-₦3,275₦491
Labour (hours)Unskilled labourer1.5 h-₦1,146₦1,719
Plant (days)Sideboom pipelayer (CAT 583 class)0.005714 day-₦1,329,210₦7,595
Plant (days)Diesel welding rig on truck (2 welders)0.008333 day-₦252,850₦2,107
Plant (days)Pipe bending machine 6-36"0.000667 day-₦956,170₦638
Plant (days)Holiday (coating) detector0.001667 day-₦25,000₦41.68
Materials₦435,735
Labour₦10,562
Plant₦10,382
Net unit rate per m₦456,678

Scope note: Excl. trench (O04), backfill (O05), hydrotest (O06), crossings. 12m joints.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦456,678₦609,550
Lagos₦484,186₦646,266
Port Harcourt₦491,840₦656,481
Ibadan₦432,260₦576,958
Osogbo (Osun)₦436,297₦582,346
Kano₦423,017₦564,621
Kaduna₦427,692₦570,860
Enugu₦445,644₦594,821
Benin City₦450,420₦601,196
Uyo₦468,478₦625,299
Jos₦432,257₦576,953
Riverine / creek site₦592,608₦790,981

Related oil & gas rates

Frequently asked questions

How much does line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench cost per m in Nigeria?

About ₦456,678 per m net in Abuja as at 15 October 2026, or about ₦609,550 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦484,186 per m and the tender rate about ₦646,266 per m.

What does the rate include?

Materials (3-layer polyethylene (3LPE) factory pipe coating, API 5L X52 line pipe 24" (610.0x12.7mm, Cellulosic electrode E6010 (root pass), Heat-shrink field joint sleeve 24" with primer, Low-hydrogen electrode E7018, Radiographic weld test) with waste allowances; labour (Coating applicator, Pipe fitter, Pipeline welder (6G coded), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Diesel welding rig on truck (2 welders), Holiday (coating) detector, Pipe bending machine 6-36", Sideboom pipelayer (CAT 583 class)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Excl. trench (O04), backfill (O05), hydrotest (O06), crossings. 12m joints.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o03-line-pipe-24-x52-3lpe-coated-string-weld-100-rt-field-jo/, prices as at 15 October 2026.