Fuel station canopy: steel frame, aluminium roof and ACP fascia: cost per m² in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦109,158per m²
Tender rate about ₦145,699 per m² with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for fuel station canopy: steel frame, aluminium roof and ACP fascia is ₦109,158 per m² in Abuja: ₦92,700 materials, ₦11,839 labour and ₦4,620 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦145,699 per m².
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Structural steel sections (UB/UC/PFC/angle), per tonne | 0.045 tonne | 5% | ₦1,450,000 | ₦68,512 |
| Material | Aluminium composite panel 4mm, per m2 | 0.35 m² | 10% | ₦22,000 | ₦8,470 |
| Material | Aluminium longspan 0.55mm, caliper (industrial) | 1.1 m² | - | ₦13,200 | ₦14,520 |
| Material | Bolt & nut M16x100 grade 8.8 with washers | 0.6 unit | 5% | ₦800 | ₦504 |
| Material | Red oxide anti-rust primer, 4L | 0.03 tin | 5% | ₦22,000 | ₦693 |
| Labour (hours) | Welder / fabricator | 1.5 h | - | ₦2,948 | ₦4,421 |
| Labour (hours) | Steel erector | 1.2 h | - | ₦3,275 | ₦3,930 |
| Labour (hours) | Aluminium fabricator / glazier | 0.6 h | - | ₦2,948 | ₦1,768 |
| Labour (hours) | Unskilled labourer | 1.5 h | - | ₦1,146 | ₦1,719 |
| Plant (days) | Mobile crane 25t | 0.004 day | - | ₦749,240 | ₦2,997 |
| Plant (days) | Welding generator 400A (diesel) | 0.01 day | - | ₦162,280 | ₦1,623 |
| Materials | ₦92,700 | ||||
| Labour | ₦11,839 | ||||
| Plant | ₦4,620 | ||||
| Net unit rate per m² | ₦109,158 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m² | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦109,158 | ₦145,699 |
| Lagos | ₦115,898 | ₦154,695 |
| Port Harcourt | ₦116,352 | ₦155,300 |
| Ibadan | ₦101,925 | ₦136,044 |
| Osogbo (Osun) | ₦102,352 | ₦136,614 |
| Kano | ₦99,479 | ₦132,779 |
| Kaduna | ₦100,761 | ₦134,490 |
| Enugu | ₦104,844 | ₦139,940 |
| Benin City | ₦106,100 | ₦141,617 |
| Uyo | ₦110,302 | ₦147,225 |
| Jos | ₦101,780 | ₦135,851 |
| Riverine / creek site | ₦140,000 | ₦186,865 |
Related oil & gas rates
- O01 Line pipe 8" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦115,949 per m
- O02 Line pipe 12" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦191,124 per m
- O03 Line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦456,678 per m
- O04 Pipeline trench excavation 1.0m wide x 1.5m deep by excavator, spoil alongside₦4,483 per m
- O05 Backfill pipeline trench with 300mm sand padding and excavated material, compacted₦4,969 per m
- O06 Hydrostatic test, dewatering and drying of 12" pipeline₦552 per m
- O07 HDD river/road crossing for 12" X52 3LPE pipeline incl. drilling fluid₦392,688 per m
- O08 Magnesium anode 17lb installed with cable and test post share₦180,520 per unit
- O09 Install 12" ANSI 150 gate valve with 2 weld-neck flanges, gaskets and bolting₦6,506,061 per unit
- O10 Pipeline marker post set in concrete₦48,573 per unit
- O11 Underground fuel tank 33,000L installed: excavation, sand surround, concrete anchor slab₦11,079,138 per unit
- O12 Fuel dispenser installed with 6m 2" seamless product line and electrics₦12,285,101 per unit
- O14 Abrasive blast clean to Sa2.5 and apply 3-coat epoxy system to steelwork₦38,872 per m²
- O15 Radiographic testing of pipeline weld (service, incl. film)₦35,573 per unit
- O16 Fabricate and erect steel storage tank shell/bottom/roof, per tonne of plate₦2,536,956 per tonne
- O17 Install 12" pig launcher/receiver incl. tie-in welds₦85,195,000 per unit
Frequently asked questions
How much does fuel station canopy: steel frame, aluminium roof and ACP fascia cost per m² in Nigeria?
About ₦109,158 per m² net in Abuja as at 15 October 2026, or about ₦145,699 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦115,898 per m² and the tender rate about ₦154,695 per m².
What does the rate include?
Materials (Aluminium composite panel 4mm, Aluminium longspan 0.55mm, Bolt & nut M16x100 grade 8.8 with washers, Red oxide anti-rust primer, Structural steel sections (UB/UC/PFC/angle)) with waste allowances; labour (Aluminium fabricator / glazier, Steel erector, Unskilled labourer, Welder / fabricator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Mobile crane 25t, Welding generator 400A (diesel)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o13-fuel-station-canopy-steel-frame-aluminium-roof-and-acp-f/, prices as at 15 October 2026.