Pipeline marker post set in concrete: cost per unit in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦48,573per unit
Tender rate about ₦64,833 per unit with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for pipeline marker post set in concrete is ₦48,573 per unit in Abuja: ₦46,854 materials, ₦1,719 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦64,833 per unit.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Pipeline marker post (steel, painted, with plate) | 1 unit | - | ₦45,000 | ₦45,000 |
| Material | OPC 42.5 cement, 50kg bag - adopted market average | 0.15 bag | 3% | ₦12,000 | ₦1,854 |
| Labour (hours) | Unskilled labourer | 1.5 h | - | ₦1,146 | ₦1,719 |
| Materials | ₦46,854 | ||||
| Labour | ₦1,719 | ||||
| Plant | ₦0 | ||||
| Net unit rate per unit | ₦48,573 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per unit | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦48,573 | ₦64,833 |
| Lagos | ₦51,522 | ₦68,769 |
| Port Harcourt | ₦52,236 | ₦69,721 |
| Ibadan | ₦45,887 | ₦61,247 |
| Osogbo (Osun) | ₦46,269 | ₦61,758 |
| Kano | ₦44,864 | ₦59,882 |
| Kaduna | ₦45,384 | ₦60,576 |
| Enugu | ₦47,292 | ₦63,123 |
| Benin City | ₦47,795 | ₦63,795 |
| Uyo | ₦49,721 | ₦66,365 |
| Jos | ₦45,852 | ₦61,201 |
| Riverine / creek site | ₦62,802 | ₦83,824 |
Related oil & gas rates
- O01 Line pipe 8" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦115,949 per m
- O02 Line pipe 12" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦191,124 per m
- O03 Line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦456,678 per m
- O04 Pipeline trench excavation 1.0m wide x 1.5m deep by excavator, spoil alongside₦4,483 per m
- O05 Backfill pipeline trench with 300mm sand padding and excavated material, compacted₦4,969 per m
- O06 Hydrostatic test, dewatering and drying of 12" pipeline₦552 per m
- O07 HDD river/road crossing for 12" X52 3LPE pipeline incl. drilling fluid₦392,688 per m
- O08 Magnesium anode 17lb installed with cable and test post share₦180,520 per unit
- O09 Install 12" ANSI 150 gate valve with 2 weld-neck flanges, gaskets and bolting₦6,506,061 per unit
- O11 Underground fuel tank 33,000L installed: excavation, sand surround, concrete anchor slab₦11,079,138 per unit
- O12 Fuel dispenser installed with 6m 2" seamless product line and electrics₦12,285,101 per unit
- O13 Fuel station canopy: steel frame, aluminium roof and ACP fascia₦109,158 per m²
- O14 Abrasive blast clean to Sa2.5 and apply 3-coat epoxy system to steelwork₦38,872 per m²
- O15 Radiographic testing of pipeline weld (service, incl. film)₦35,573 per unit
- O16 Fabricate and erect steel storage tank shell/bottom/roof, per tonne of plate₦2,536,956 per tonne
- O17 Install 12" pig launcher/receiver incl. tie-in welds₦85,195,000 per unit
Frequently asked questions
How much does pipeline marker post set in concrete cost per unit in Nigeria?
About ₦48,573 per unit net in Abuja as at 15 October 2026, or about ₦64,833 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦51,522 per unit and the tender rate about ₦68,769 per unit.
What does the rate include?
Materials (OPC 42.5 cement, Pipeline marker post (steel) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o10-pipeline-marker-post-set-in-concrete/, prices as at 15 October 2026.