BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Backfill pipeline trench with 300mm sand padding and excavated material, compacted: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦4,969per m

Tender rate about ₦6,633 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for backfill pipeline trench with 300mm sand padding and excavated material, compacted is ₦4,969 per m in Abuja: ₦2,205 materials, ₦573 labour and ₦2,191 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,633 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFilling sand, per tonne0.6 tonne5%₦3,500₦2,205
Plant (days)Hydraulic excavator 20-22t (CAT 320/215 class)0.0025 day-₦827,850₦2,070
Plant (days)Plate compactor (petrol)0.005 day-₦24,273₦121
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦2,205
Labour₦573
Plant₦2,191
Net unit rate per m₦4,969

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦4,969₦6,633
Lagos₦5,257₦7,017
Port Harcourt₦5,292₦7,064
Ibadan₦4,635₦6,186
Osogbo (Osun)₦4,672₦6,236
Kano₦4,562₦6,089
Kaduna₦4,601₦6,141
Enugu₦4,767₦6,362
Benin City₦4,844₦6,465
Uyo₦5,015₦6,694
Jos₦4,667₦6,229
Riverine / creek site₦6,564₦8,762

Related oil & gas rates

Frequently asked questions

How much does backfill pipeline trench with 300mm sand padding and excavated material, compacted cost per m in Nigeria?

About ₦4,969 per m net in Abuja as at 15 October 2026, or about ₦6,633 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦5,257 per m and the tender rate about ₦7,017 per m.

What does the rate include?

Materials (Filling sand) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 20-22t (CAT 320/215 class), Plate compactor (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o05-backfill-pipeline-trench-with-300mm-sand-padding-and-exc/, prices as at 15 October 2026.