Backfill pipeline trench with 300mm sand padding and excavated material, compacted: cost per m in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦4,969per m
Tender rate about ₦6,633 per m with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for backfill pipeline trench with 300mm sand padding and excavated material, compacted is ₦4,969 per m in Abuja: ₦2,205 materials, ₦573 labour and ₦2,191 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,633 per m.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Filling sand, per tonne | 0.6 tonne | 5% | ₦3,500 | ₦2,205 |
| Plant (days) | Hydraulic excavator 20-22t (CAT 320/215 class) | 0.0025 day | - | ₦827,850 | ₦2,070 |
| Plant (days) | Plate compactor (petrol) | 0.005 day | - | ₦24,273 | ₦121 |
| Labour (hours) | Unskilled labourer | 0.5 h | - | ₦1,146 | ₦573 |
| Materials | ₦2,205 | ||||
| Labour | ₦573 | ||||
| Plant | ₦2,191 | ||||
| Net unit rate per m | ₦4,969 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦4,969 | ₦6,633 |
| Lagos | ₦5,257 | ₦7,017 |
| Port Harcourt | ₦5,292 | ₦7,064 |
| Ibadan | ₦4,635 | ₦6,186 |
| Osogbo (Osun) | ₦4,672 | ₦6,236 |
| Kano | ₦4,562 | ₦6,089 |
| Kaduna | ₦4,601 | ₦6,141 |
| Enugu | ₦4,767 | ₦6,362 |
| Benin City | ₦4,844 | ₦6,465 |
| Uyo | ₦5,015 | ₦6,694 |
| Jos | ₦4,667 | ₦6,229 |
| Riverine / creek site | ₦6,564 | ₦8,762 |
Related oil & gas rates
- O01 Line pipe 8" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦115,949 per m
- O02 Line pipe 12" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦191,124 per m
- O03 Line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦456,678 per m
- O04 Pipeline trench excavation 1.0m wide x 1.5m deep by excavator, spoil alongside₦4,483 per m
- O06 Hydrostatic test, dewatering and drying of 12" pipeline₦552 per m
- O07 HDD river/road crossing for 12" X52 3LPE pipeline incl. drilling fluid₦392,688 per m
- O08 Magnesium anode 17lb installed with cable and test post share₦180,520 per unit
- O09 Install 12" ANSI 150 gate valve with 2 weld-neck flanges, gaskets and bolting₦6,506,061 per unit
- O10 Pipeline marker post set in concrete₦48,573 per unit
- O11 Underground fuel tank 33,000L installed: excavation, sand surround, concrete anchor slab₦11,079,138 per unit
- O12 Fuel dispenser installed with 6m 2" seamless product line and electrics₦12,285,101 per unit
- O13 Fuel station canopy: steel frame, aluminium roof and ACP fascia₦109,158 per m²
- O14 Abrasive blast clean to Sa2.5 and apply 3-coat epoxy system to steelwork₦38,872 per m²
- O15 Radiographic testing of pipeline weld (service, incl. film)₦35,573 per unit
- O16 Fabricate and erect steel storage tank shell/bottom/roof, per tonne of plate₦2,536,956 per tonne
- O17 Install 12" pig launcher/receiver incl. tie-in welds₦85,195,000 per unit
Frequently asked questions
How much does backfill pipeline trench with 300mm sand padding and excavated material, compacted cost per m in Nigeria?
About ₦4,969 per m net in Abuja as at 15 October 2026, or about ₦6,633 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦5,257 per m and the tender rate about ₦7,017 per m.
What does the rate include?
Materials (Filling sand) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 20-22t (CAT 320/215 class), Plate compactor (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o05-backfill-pipeline-trench-with-300mm-sand-padding-and-exc/, prices as at 15 October 2026.