Fuel dispenser installed with 6m 2" seamless product line and electrics: cost per unit in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦12,285,101per unit
Tender rate about ₦16,397,500 per unit with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for fuel dispenser installed with 6m 2" seamless product line and electrics is ₦12,285,101 per unit in Abuja: ₦12,223,040 materials, ₦62,061 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦16,397,500 per unit.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Fuel dispenser, 2-nozzle electronic | 1 unit | - | ₦12,130,300 | ₦12,130,300 |
| Material | A106 Gr.B seamless pipe 2" sch40 (5.44 kg/m), per m | 6 m | 5% | ₦14,721 | ₦92,740 |
| Labour (hours) | Pipe fitter | 8 h | - | ₦4,912 | ₦39,300 |
| Labour (hours) | Electrician | 6 h | - | ₦3,029 | ₦18,176 |
| Labour (hours) | Unskilled labourer | 4 h | - | ₦1,146 | ₦4,585 |
| Materials | ₦12,223,040 | ||||
| Labour | ₦62,061 | ||||
| Plant | ₦0 | ||||
| Net unit rate per unit | ₦12,285,101 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per unit | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦12,285,101 | ₦16,397,500 |
| Lagos | ₦13,023,448 | ₦17,383,007 |
| Port Harcourt | ₦13,259,841 | ₦17,698,531 |
| Ibadan | ₦11,661,537 | ₦15,565,200 |
| Osogbo (Osun) | ₦11,780,664 | ₦15,724,205 |
| Kano | ₦11,413,973 | ₦15,234,765 |
| Kaduna | ₦11,538,065 | ₦15,400,396 |
| Enugu | ₦12,028,228 | ₦16,054,640 |
| Benin City | ₦12,151,700 | ₦16,219,443 |
| Uyo | ₦12,642,483 | ₦16,874,515 |
| Jos | ₦11,660,295 | ₦15,563,543 |
| Riverine / creek site | ₦15,958,219 | ₦21,300,183 |
Related oil & gas rates
- O01 Line pipe 8" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦115,949 per m
- O02 Line pipe 12" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦191,124 per m
- O03 Line pipe 24" X52, 3LPE-coated: string, weld (100% RT), field-joint coat, lower-in and tie-in in prepared trench₦456,678 per m
- O04 Pipeline trench excavation 1.0m wide x 1.5m deep by excavator, spoil alongside₦4,483 per m
- O05 Backfill pipeline trench with 300mm sand padding and excavated material, compacted₦4,969 per m
- O06 Hydrostatic test, dewatering and drying of 12" pipeline₦552 per m
- O07 HDD river/road crossing for 12" X52 3LPE pipeline incl. drilling fluid₦392,688 per m
- O08 Magnesium anode 17lb installed with cable and test post share₦180,520 per unit
- O09 Install 12" ANSI 150 gate valve with 2 weld-neck flanges, gaskets and bolting₦6,506,061 per unit
- O10 Pipeline marker post set in concrete₦48,573 per unit
- O11 Underground fuel tank 33,000L installed: excavation, sand surround, concrete anchor slab₦11,079,138 per unit
- O13 Fuel station canopy: steel frame, aluminium roof and ACP fascia₦109,158 per m²
- O14 Abrasive blast clean to Sa2.5 and apply 3-coat epoxy system to steelwork₦38,872 per m²
- O15 Radiographic testing of pipeline weld (service, incl. film)₦35,573 per unit
- O16 Fabricate and erect steel storage tank shell/bottom/roof, per tonne of plate₦2,536,956 per tonne
- O17 Install 12" pig launcher/receiver incl. tie-in welds₦85,195,000 per unit
Frequently asked questions
How much does fuel dispenser installed with 6m 2" seamless product line and electrics cost per unit in Nigeria?
About ₦12,285,101 per unit net in Abuja as at 15 October 2026, or about ₦16,397,500 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦13,023,448 per unit and the tender rate about ₦17,383,007 per unit.
What does the rate include?
Materials (A106 Gr.B seamless pipe 2" sch40 (5.44 kg/m), Fuel dispenser) with waste allowances; labour (Electrician, Pipe fitter, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o12-fuel-dispenser-installed-with-6m-2-seamless-product-line/, prices as at 15 October 2026.