Radiographic testing of pipeline weld (service, incl. film): cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦35,573per unit

Tender rate about ₦47,481 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for radiographic testing of pipeline weld (service, incl. film) is ₦35,573 per unit in Abuja: ₦35,000 materials, ₦573 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦47,481 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRadiographic weld test, per joint (incl. film)1 unit-₦35,000₦35,000
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦35,000
Labour₦573
Plant₦0
Net unit rate per unit₦35,573

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦35,573₦47,481
Lagos₦37,719₦50,345
Port Harcourt₦38,344₦51,180
Ibadan₦33,708₦44,992
Osogbo (Osun)₦34,030₦45,421
Kano₦32,980₦44,020
Kaduna₦33,347₦44,510
Enugu₦34,758₦46,394
Benin City₦35,120₦46,876
Uyo₦36,537₦48,768
Jos₦33,697₦44,977
Riverine / creek site₦46,130₦61,572

Related oil & gas rates

Frequently asked questions

How much does radiographic testing of pipeline weld (service, incl. film) cost per unit in Nigeria?

About ₦35,573 per unit net in Abuja as at 15 October 2026, or about ₦47,481 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦37,719 per unit and the tender rate about ₦50,345 per unit.

What does the rate include?

Materials (Radiographic weld test) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/o15-radiographic-testing-of-pipeline-weld-service-incl-film/, prices as at 15 October 2026.