Laminated elastomeric bearing supplied and installed: cost per dm3 in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦4,343per dm3

Tender rate about ₦5,797 per dm3 with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for laminated elastomeric bearing supplied and installed is ₦4,343 per dm3 in Abuja: ₦4,106 materials, ₦237 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦5,797 per dm3.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialLaminated elastomeric bearing, per dm31 dm3-₦4,106₦4,106
Labour (hours)Mason / bricklayer0.05 h-₦2,456₦123
Labour (hours)Unskilled labourer0.1 h-₦1,146₦115
Materials₦4,106
Labour₦237
Plant₦0
Net unit rate per dm3₦4,343

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per dm3Tender rate incl. OH&P and VAT
Abuja (FCT)₦4,343₦5,797
Lagos₦4,608₦6,151
Port Harcourt₦4,660₦6,219
Ibadan₦4,090₦5,460
Osogbo (Osun)₦4,119₦5,498
Kano₦3,996₦5,334
Kaduna₦4,045₦5,398
Enugu₦4,213₦5,624
Benin City₦4,259₦5,685
Uyo₦4,431₦5,914
Jos₦4,086₦5,453
Riverine / creek site₦5,599₦7,473

Related bridges & heavy structures rates

Frequently asked questions

How much does laminated elastomeric bearing supplied and installed cost per dm3 in Nigeria?

About ₦4,343 per dm3 net in Abuja as at 15 October 2026, or about ₦5,797 per dm3 as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦4,608 per dm3 and the tender rate about ₦6,151 per dm3.

What does the rate include?

Materials (Laminated elastomeric bearing) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/q02-laminated-elastomeric-bearing-supplied-and-installed/, prices as at 15 October 2026.