BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Bridge deck waterproofing membrane on primed deck: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦12,393per m²

Tender rate about ₦16,541 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for bridge deck waterproofing membrane on primed deck is ₦12,393 per m² in Abuja: ₦12,000 materials, ₦393 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦16,541 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialBridge deck waterproofing membrane, per m21.08 m²8%₦9,500₦11,081
MaterialBitumen primer, per litre0.25 litre5%₦3,500₦919
Labour (hours)Waterproofing applicator0.15 h-₦2,620₦393
Materials₦12,000
Labour₦393
Plant₦0
Net unit rate per m²₦12,393

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦12,393₦16,541
Lagos₦13,144₦17,544
Port Harcourt₦13,333₦17,796
Ibadan₦11,714₦15,635
Osogbo (Osun)₦11,814₦15,769
Kano₦11,454₦15,289
Kaduna₦11,586₦15,465
Enugu₦12,074₦16,116
Benin City₦12,202₦16,286
Uyo₦12,694₦16,943
Jos₦11,706₦15,625
Riverine / creek site₦16,032₦21,398

Related bridges & heavy structures rates

Frequently asked questions

How much does bridge deck waterproofing membrane on primed deck cost per m² in Nigeria?

About ₦12,393 per m² net in Abuja as at 15 October 2026, or about ₦16,541 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦13,144 per m² and the tender rate about ₦17,544 per m².

What does the rate include?

Materials (Bitumen primer, Bridge deck waterproofing membrane) with waste allowances; labour (Waterproofing applicator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/q07-bridge-deck-waterproofing-membrane-on-primed-deck/, prices as at 15 October 2026.