BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Deck drainage scupper installed: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦92,205per unit

Tender rate about ₦123,070 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for deck drainage scupper installed is ₦92,205 per unit in Abuja: ₦85,000 materials, ₦7,205 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦123,070 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialDeck drainage scupper with downpipe1 unit-₦85,000₦85,000
Labour (hours)Mason / bricklayer2 h-₦2,456₦4,912
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Materials₦85,000
Labour₦7,205
Plant₦0
Net unit rate per unit₦92,205

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦92,205₦123,070
Lagos₦97,881₦130,647
Port Harcourt₦98,645₦131,666
Ibadan₦86,514₦115,474
Osogbo (Osun)₦87,004₦116,128
Kano₦84,454₦112,724
Kaduna₦85,520₦114,147
Enugu₦89,064₦118,878
Benin City₦90,058₦120,205
Uyo₦93,674₦125,031
Jos₦86,370₦115,282
Riverine / creek site₦118,426₦158,068

Related bridges & heavy structures rates

Frequently asked questions

How much does deck drainage scupper installed cost per unit in Nigeria?

About ₦92,205 per unit net in Abuja as at 15 October 2026, or about ₦123,070 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦97,881 per unit and the tender rate about ₦130,647 per unit.

What does the rate include?

Materials (Deck drainage scupper with downpipe) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/q11-deck-drainage-scupper-installed/, prices as at 15 October 2026.