BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Aluminium system formwork to slab soffit (1 month hire per use): cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦6,875per m²

Tender rate about ₦9,176 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for aluminium system formwork to slab soffit (1 month hire per use) is ₦6,875 per m² in Abuja: ₦4,631 materials, ₦2,243 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦9,176 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialAluminium slab formwork system hire, per m2 per month1 m²-₦4,500₦4,500
MaterialFormwork release oil, per litre0.05 litre5%₦2,500₦131
Labour (hours)Carpenter (formwork & roof)0.6 h-₦2,784₦1,670
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦4,631
Labour₦2,243
Plant₦0
Net unit rate per m²₦6,875

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦6,875₦9,176
Lagos₦7,332₦9,786
Port Harcourt₦7,133₦9,521
Ibadan₦6,194₦8,268
Osogbo (Osun)₦6,129₦8,180
Kano₦5,990₦7,995
Kaduna₦6,103₦8,146
Enugu₦6,333₦8,453
Benin City₦6,425₦8,575
Uyo₦6,677₦8,912
Jos₦6,150₦8,208
Riverine / creek site₦8,488₦11,330

Related bridges & heavy structures rates

Frequently asked questions

How much does aluminium system formwork to slab soffit (1 month hire per use) cost per m² in Nigeria?

About ₦6,875 per m² net in Abuja as at 15 October 2026, or about ₦9,176 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦7,332 per m² and the tender rate about ₦9,786 per m².

What does the rate include?

Materials (Aluminium slab formwork system hire, Formwork release oil) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/q09-aluminium-system-formwork-to-slab-soffit-1-month-hire-pe/, prices as at 15 October 2026.