Pot bearing 2,000kN supplied, installed and grouted: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦7,277,811per unit

Tender rate about ₦9,714,035 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for pot bearing 2,000kN supplied, installed and grouted is ₦7,277,811 per unit in Abuja: ₦7,150,360 materials, ₦15,065 labour and ₦112,386 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦9,714,035 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPot bearing 2,000kN (guided/free)1 unit-₦7,091,560₦7,091,560
MaterialNon-shrink cementitious grout, 25kg2 bag5%₦28,000₦58,800
Plant (days)Mobile crane 25t0.15 day-₦749,240₦112,386
Labour (hours)Rigger / banksman4 h-₦2,620₦10,480
Labour (hours)Unskilled labourer4 h-₦1,146₦4,585
Materials₦7,150,360
Labour₦15,065
Plant₦112,386
Net unit rate per unit₦7,277,811

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦7,277,811₦9,714,035
Lagos₦7,713,657₦10,295,780
Port Harcourt₦7,858,077₦10,488,544
Ibadan₦6,911,661₦9,225,318
Osogbo (Osun)₦6,984,659₦9,322,751
Kano₦6,767,900₦9,033,434
Kaduna₦6,839,856₦9,129,476
Enugu₦7,129,543₦9,516,135
Benin City₦7,203,596₦9,614,977
Uyo₦7,493,434₦10,001,837
Jos₦6,913,607₦9,227,915
Riverine / creek site₦9,469,380₦12,639,225

Related bridges & heavy structures rates

Frequently asked questions

How much does pot bearing 2,000kN supplied, installed and grouted cost per unit in Nigeria?

About ₦7,277,811 per unit net in Abuja as at 15 October 2026, or about ₦9,714,035 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦7,713,657 per unit and the tender rate about ₦10,295,780 per unit.

What does the rate include?

Materials (Non-shrink cementitious grout, Pot bearing 2) with waste allowances; labour (Rigger / banksman, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/q03-pot-bearing-2-000kn-supplied-installed-and-grouted/, prices as at 15 October 2026.