BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Flush door 900x2100 with frame & ironmongery, supply & fix: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦123,517per unit

Tender rate about ₦164,864 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for flush door 900x2100 with frame & ironmongery, supply & fix is ₦123,517 per unit in Abuja: ₦111,236 materials, ₦12,281 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦164,864 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFlush door 900x2100 with hardwood frame & ironmongery (supply)1 unit-₦110,000₦110,000
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.1 bag3%₦12,000₦1,236
Labour (hours)Carpenter (formwork & roof)4 h-₦2,784₦11,135
Labour (hours)Unskilled labourer1 h-₦1,146₦1,146
Materials₦111,236
Labour₦12,281
Plant₦0
Net unit rate per unit₦123,517

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦123,517₦164,864
Lagos₦131,174₦175,084
Port Harcourt₦131,802₦175,922
Ibadan₦115,499₦154,162
Osogbo (Osun)₦115,997₦154,827
Kano₦112,660₦150,373
Kaduna₦114,141₦152,350
Enugu₦118,836₦158,616
Benin City₦120,194₦160,429
Uyo₦125,012₦166,860
Jos₦115,254₦153,834
Riverine / creek site₦158,116₦211,045

Related doors & windows rates

Frequently asked questions

How much does flush door 900x2100 with frame & ironmongery, supply & fix cost per unit in Nigeria?

About ₦123,517 per unit net in Abuja as at 15 October 2026, or about ₦164,864 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦131,174 per unit and the tender rate about ₦175,084 per unit.

What does the rate include?

Materials (Flush door 900x2100 with hardwood frame & ironmongery (supply), OPC 42.5 cement) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/j01-flush-door-900x2100-with-frame-and-ironmongery-supply-an/, prices as at 15 October 2026.