Stick curtain wall, tinted glass, s&f: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦260,229per m²

Tender rate about ₦347,340 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for stick curtain wall, tinted glass, s&f is ₦260,229 per m² in Abuja: ₦260,000 materials, ₦229 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦347,340 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialStick curtain wall, tinted glass - supply & fix1 m²-₦260,000₦260,000
Labour (hours)Unskilled labourer0.2 h-₦1,146₦229
Materials₦260,000
Labour₦229
Plant₦0
Net unit rate per m²₦260,229

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦260,229₦347,340
Lagos₦275,848₦368,187
Port Harcourt₦281,018₦375,088
Ibadan₦247,183₦329,927
Osogbo (Osun)₦249,772₦333,382
Kano₦241,972₦322,971
Kaduna₦244,579₦326,451
Enugu₦254,983₦340,338
Benin City₦257,588₦343,815
Uyo₦267,995₦357,705
Jos₦247,179₦329,921
Riverine / creek site₦338,252₦451,481

Related doors & windows rates

Frequently asked questions

How much does stick curtain wall, tinted glass, s&f cost per m² in Nigeria?

About ₦260,229 per m² net in Abuja as at 15 October 2026, or about ₦347,340 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦275,848 per m² and the tender rate about ₦368,187 per m².

What does the rate include?

Materials (Stick curtain wall) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/j08-stick-curtain-wall-tinted-glass-s-and-f/, prices as at 15 October 2026.