uPVC casement window, s&f incl. making good: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦150,984per m²

Tender rate about ₦201,526 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for uPVC casement window, s&f incl. making good is ₦150,984 per m² in Abuja: ₦150,247 materials, ₦737 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦201,526 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialuPVC casement window, double seal - supply & fix1 m²-₦150,000₦150,000
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.02 bag3%₦12,000₦247
Labour (hours)Mason / bricklayer0.3 h-₦2,456₦737
Materials₦150,247
Labour₦737
Plant₦0
Net unit rate per m²₦150,984

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦150,984₦201,526
Lagos₦160,058₦213,637
Port Harcourt₦162,967₦217,520
Ibadan₦143,324₦191,302
Osogbo (Osun)₦144,790₦193,258
Kano₦140,283₦187,242
Kaduna₦141,807₦189,277
Enugu₦147,832₦197,318
Benin City₦149,349₦199,343
Uyo₦155,381₦207,394
Jos₦143,310₦191,282
Riverine / creek site₦196,132₦261,786

Related doors & windows rates

Frequently asked questions

How much does uPVC casement window, s&f incl. making good cost per m² in Nigeria?

About ₦150,984 per m² net in Abuja as at 15 October 2026, or about ₦201,526 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦160,058 per m² and the tender rate about ₦213,637 per m².

What does the rate include?

Materials (OPC 42.5 cement, uPVC casement window) with waste allowances; labour (Mason / bricklayer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/j06-upvc-casement-window-s-and-f-incl-making-good/, prices as at 15 October 2026.